Water supply for municipality of Vyšný Kazimír – completion

  • Investor
    Obec Vyšný Kazimír č 57, 094 09 Sedliská
  • Implementation period
    36 mesiacov
  • Location
    Vyšný Kazimír
Construction description:

The subject of the construction is the completion of 11 buildings, which are in various stages of completion, due to the gradual financing by the investor. The building consists of:

  • SO 01 Inlet to the petrol station
  • SO 02 Construction part of the pumping station
  • SO 03 Electrical LV connection of the pumping station
  • SO 04 Feed line
  • SA 06 Water tank – change no.1
  • SO 07 Waterway access road
  • SO 09 Waste water tank
  • SO 11 Distribution network
  • SO 12 Water connections
  • PS 01 Technological part of the pumping station
  • PS 02 Technological part of the water tank